Welcome to PMConnection

     

Menu
Home
Current Newsletter
Event Calendar
Research Center
Exclusive Articles
More

Related Sites

Related Books 4
 
Project Management for Dummies

 
Managing Projects with Microsoft Office Project 2007 (Exam 70-632)

 
Rita''s Pocket PMP Exam

 
Program Management Professional (PgMP) Study Guide

 
Enterprise Project Management Using Microsoft Office Project Server 2007

MS Project: Color Coding Tasks Based Upon Date Range
PMConnection Articles
So you would like to be able to quickly examine your project schedule to see which tasks your team should be working on this week…or…maybe you would like to see which tasks you should work on next week. The following is a dynamic approach, quick to implement, and will meet this need.

1. From within your schedule, click on >View, >More Views, select Gantt Chart, and click on Copy.



2. For Name, type “Date Range View”

3. For Filter, select Date Range…

4. Check Highlight Filter and click on OK. Click on Close to close the More Views dialogue box.



5. Click on >View and select the new >Date Range View



6. A dialogue box will appear asking for you to input the beginning date. Note that this will “Show tasks that start or finish after” the selected date. Always select the first day of the week even if it falls on a Sunday. Click on OK.



7. Another dialogue box will appear asking for you to input the ending date. Note that this will show tasks that start or finish “before” the selected date. Always select the last day of the week even if it falls on a Saturday. Click on OK.



8. Now all of the tasks that are scheduled to be worked on within the selected date range will be automatically highlighted.



Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Sunday, March 15 @ 12:23:03 CDT (671 reads)
(Read More... | Score: 4.66)

MS Project: Export MS Project to Excel, Update, Then Import Updates Back Into MS Project
PMConnection Articles
1. Open the project in MS Project

2. Click on >File, >Save As. Choose the location where you would like this file to be saved.

3. Click on the dropdown for Save as type and select Microsoft Excel Workbook (*.xls)


4. Click on Save

5. The Project Export Wizard will open, click on Next



6. Choose Selected Data and click on Next



7. Choose New Map. Click on Next.



8. Select Tasks and ensure Export includes headers. Click on Next.



9. The Task Mapping dialogue box will appear. Click on the dropdown in the first row under “From: Microsoft Office Project field” and select ID.



10. Click on the dropdown in the second row and input Name.



11. Continue adding the following fields:

ID
Name
Start
Finish
% Complete
Resource Names



12. Click on Next

13. Click on Save Map (for future reuse)



14. Name this map, then click on Save.



15. Click on Finish


16. Let’s say I am the Project Manager for this project and I would like to get updates from my team on their progress. I could attach this Excel file to an email and send it to the team members.

17. Let’s say that the date is 11/07/08 and Angie Krause (a team member) would like to update the progress on her tasks.

18. Open the file in Excel. Click on >Data, >Filter



19. Click on the dropdown for the Resource Names column, uncheck “Select All” and check Angie Krause. Click on OK.



20. Now Angie sees only the tasks assigned to her.


21. The next step is to update the Start date, the Finish date and the % Complete of these tasks. The objective is to bring this information in line with reality.

22. The first three tasks started and completed as expected, so Angie input 100% on those tasks.

23. The fourth task (Task ID 10: Identify budget requirements) is only 50% Complete and instead of completing on 11/07/08, Angie updates the Finish date to be Tuesday 11/11/08.


24. Angie then saves and closes this file and sends it back to the project manager.

25. To incorporate Angies updates back into the project, we must first open the project in MS Project.

26. Within MS Project, click on Open and browse to where Angies updated Microsoft Excel file has been saved. You will need to click on the dropdown in the bottom right to see “All files”.



27. Select Angies updated file in Excel and click on Open. The Import Wizard will again open. Click on Next.



28. Select Use Existing Map and click on Next.



29. Select the map that we saved earlier (Export to Excel) in step 14 and click on Next.



30. Select Merge data into active project and click on Next.



31. Ensure Task and Import includes headers is checked. Click on Next.



32. All fields should already be mapped correctly.



33. Click on ID and then click on Set Merge Key



34. Click on Next, then click on Finish



35. If we drill into the details of this project file and insert the % Complete field, we can see Angies updates have been applied.



36. By examining the Tracking Gantt view, we can see the impact of Angies updates to our baseline.


*A few Cautions:

1. This approach forces Microsoft Project to impose a Finish No Earlier than constraint on any task that is not 100% Complete. As a work-around, the project manager could modify the Excel file prior to distributing so only current period tasks are included.

2. Because we are exporting Task level information, this approach only works with one resource assigned to each task. If you have multiple resources assigned to tasks, you would want to work with the Assignments table on the Export map instead of the Task table.

3. You may want to password protect all columns within the Excel document except Start, Finish and % Complete to keep these fields from being altered.

4. Do NOT add new tasks to your project until after importing the updates. Remember that alignment between the Excel and the MS Project file data is established by the ID column. Inserting a new task will create a new ID thus causing your files to be out of alignment.


Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Wednesday, March 11 @ 00:05:11 CDT (4468 reads)
(Read More... | Score: 4.5)

MS Project: Copy Data from Microsoft Project and Paste into Excel
PMConnection Articles
1. Create a view that contains the desired data

2. Select the data you would like to copy within Microsoft Project


3. Click on >Edit, >Copy Task (Ctrl-C)

4. Within Excel, click on Paste


Note that the selected information is pasted accurately, but it lacks the column headings, the WBS or outline structure and it does not retain the bold formatting for Summary Tasks or the Project Summary Task. Also note that the date format now includes the time.

This approach is quick and simple but makes it very tough to decipher the details of this project. Additional work or formatting may be required to get this file in a workable state.


See "Getting Data From Microsoft Project to Excel" for other options.



Social Bookmark this page

RSS Feed for Exclusive Articles


Posted by webadmin on Saturday, November 15 @ 00:23:02 CST (1555 reads)
(Read More... | Score: 0)

MS Project: Getting Data From Microsoft Project to Excel
PMConnection Articles
There are a number of ways in which we can get data from Microsoft Project to Excel.  Some are easy.  Some are harder.  Some depend upon the version of Microsoft Project you leverage.  This article will list the different ways and the strengths and weaknesses of each approach.  Future articles will provide detailed steps on the respective approaches.

Note:  This list is built with a maturity model concept.  The items that appear first are relatively easy to produce.  Options near the end are more sophisticated.

1.    Copy and Paste (all versions of Project)
    a.    Develop the view you like in Microsoft Project, copy the data, move to Excel and paste.
    b.    Plus – Easy!
    c.    Minus – Does not retain outline structure or formatting



2.    Leverage Online Tool (2000 – 2007)
    a.    There is a website you can leverage to convert your Microsoft Project data to Excel
    b.    Plus – Easy and maintains outline structure and formatting
    c.    Minus – Limited to preset fields



3.    Save Microsoft Project as an Excel File (2003 – 2007)
    a.    A nice built in wizard walks you through this process
    b.    Plus – You get to decide which fields get exported
    c.    Minus - Does not retain outline structure or formatting



4.    Analyze Timescaled Data in Excel (2003 and maybe 2007)
    a.    There is a built in feature within Microsoft Project 2003 (and maybe your version of 2007) called Analyze Timescaled in Excel
    b.    Plus – Easy to create, great graphs
    c.    Minus – Does not retain outline structure or formatting, selected fields are displayed below each task



5.    Visual Reports (2007)
    a.    A great new feature of Microsoft Project 2007.  Can be found from >Reports, >Visual Reports.
    b.    Plus – Many great pre-configured reports
    c.    Plus – Data can easily be manipulated in Excel using Pivot table
    d.    Minus – To be of real value, you must be good with Pivot tables!



6.    Export Data From Microsoft Project to Excel and Maintain the Outline Structure (2003)
    a.    This is an “old school” work around of saving the file as .html and then converting that to a .xls file.
    b.    Plus – Maintains outline structure and formatting
    c.    Minus – A little tricky if you want to create your own map



7.    Export Data From PWA to Excel and Maintain the Outline Structure (Project Server 2003)
    a.    Simple built in feature of Microsoft Project Server 2003.  Drill into Project Details of PWA and then Export Grid to Excel.
    b.    Plus – Easy
    c.    Minus – Requires Project Server, Lacks Timephased data, Getting the data you desire may require building a new PWA View.



8.    Export Data From PWA to Excel and Maintain the Outline Structure (Project Server 2007)
    a.    Simple built in feature of Microsoft Project Server 2007.  Drill into Project Details of PWA and then click on >Actions, > Export Grid to Excel.
    b.    Plus – Easy
    c.    Minus – Requires Project Server, Lacks Timephased data, , Getting the data you desire may require building a new PWA View.



9.    Export Data From Microsoft Project to Excel, Update It, and Import Updates From Excel Back into Microsoft Project (2003 and 2007)
    a.    Yes, it’s possible!  Requires creating a map.
    b.    Plus – Great for importing updates
    c.    Minus – A bit cumbersome



10.    Macro (2000 – 2007)
    a.    If you are comfortable with macros, then this may be your solution!
    b.    Plus – Retains outline structure and formatting
    c.    Minus – Requires a little knowledge of macros




Social Bookmark this page

RSS Feed for Exclusive Articles


Posted by webadmin on Saturday, November 15 @ 00:19:10 CST (13815 reads)
(Read More... | Score: 4.18)

MS Project: Dynamic Color Coded Phases
PMConnection Articles
How to Create Multi Color Summary Bar Based Upon Phase

The following steps will show you how to create this:


Note that color formatting is dynamic and will adjust as Duration of the phase increases or decreases.

1.  Must establish consistent Phase names. Example:

- Planning
- Execution
- Closure

2.  Must establish consistent Milestone names. Also useful to have Acronym for milestone names. Example:

Milestone - Acronym
- Planning Complete – PC
- Execution Complete – EC
- Closure Project - CP

3.  Open MS Project

4.  Establish Phase Names and Milestone Names:



5.  Select the Milestones, right click and click on Task Information.



6.  Place a check in “Roll up to Gantt bar to Summary”



7.  Click on OK. Rolled up Milestones will now appear on Summary Bars



8.  Right click on the Gantt Chart and click on Bar Styles



9.  Click on *Rolled Up Milestone, then click on the Text tab. For Bottom, select Name.



10.  Click on OK. Milestone Names will now appear below the Rolled up Milestones on the Summary Bars



11.  Insert Flag 1, Flag 2, and Flag 3 columns



12.  Right click on Flag 1 and click on Customize Fields

13.  Click on Rename and input “Planning Flag”



14.  Click on OK

15.  Click on Formula

16.  Input the following formula: [Name]=“Planning”



17.  Click on OK

18.  For “Calculation for task and group summary rows”, ensure “Use Formula” is enabled.



19.  Click on OK

20.  “Yes” should now automatically appear under the Planning Flag for the Planning Summary Task:



21.  Right click on Flag 2 and click on Customize Fields

22.  Click on Rename and input “Execution Flag”

23.  Click on OK.

24.  Click on Formula

25.  Input the following formula: [Name]=“Execution”

26.  Click on OK

27.  For “Calculation for task and group summary rows”, ensure “Use Formula” is enabled.

28.  Click on OK

29.  Right click on Flag 3 and click on Customize Fields

30.  Click on Rename and input “Closure Flag”

31.  Click on OK.

32.  Click on Formula

33.  Input the following formula: [Name]=“Closure”

34.  Click on OK

35.  For “Calculation for task and group summary rows”, ensure “Use Formula” is enabled.

36.  Click on OK



37.  You may now hide the three flag fields

38.  Click on Show Outline Level 1



39.  Right click on the Gantt chart area and click on Bar Styles

40.  Under Name, click on Summary

41.  Click on Cut Row

42.  Click on Paste Row four times



43.  Move to the second Summary under Name and input “Rolled Up Summary Planning”



44.  Move to the Show For column, input a coma after Summary, click on the dropdown, select Rolled up. Input a coma after Rolled up, click on the dropdown and select Flag 1. Then click on Rolled up Summary Planning



45.  On the Bars tab for Start, Middle and End, click on the dropdown and select the color you would like to appear for the Planning Phase.



46.  Complete steps 43 through 45 for the 3rd and 4th Rolled Up Summary



47.  Click on OK. Colors will now appear on Summary row



48.  To add the Phase Names below each phase, right click on the Gantt Chart and click on Bar Styles

49.  Click on Rolled Up Summary Planning under Name

50.  Click on the Text Tab

51.  For Bottom, Select Name



52.  Click on OK

53.  Complete steps 49 through 52 for Rolled Up Summary Execution and Rolled Up Summary Closure

54.  Click on OK




Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Monday, September 22 @ 01:22:36 CDT (1082 reads)
(Read More... | Score: 5)

MS Project: Understanding How Microsoft Project Thinks
PMConnection Articles
There are a number of factors that dictate how Microsoft Project “thinks”.

The two main factors are:

  • The Scheduling Formula
  • The Task Type
The Scheduling Formula leverages three variables:

  • Units - The percentage of time required by a resource or resources to complete the task
  • Duration - The number of working days required to complete the task
  • Work - The effort required to complete the task
Many people say that the scheduling formula is: Units x Duration = Work

When you initially assign a Resource to a Task, this is the formula that is leveraged. Let’s demonstrate:

We will create Task 1 that is 5 days in Duration



We will now assign a Resource to this task



As soon as we assign this Resource to this task, Work changes to 40 hours.

Here is the how that number was calculated:

Units x Duration = Work
100% x (5*8) = 40
Or
100% x 40 = 40 hours


But using simple math, we can re-write our equation to solve for a different variable.

Our original formula solves for Work:
Units x Duration = Work


But we could re-write the formula to solve for Units:
Work / Duration = Units


Or we could re-write the formula to solve for Duration:
Work / Units = Duration


So we have shown that The Scheduling Formula can actually be written three different ways:

Units x Duration = Work
Work / Duration = Units
Work / Units = Duration


Now let’s prove that Microsoft Project also thinks this way.

In order to demonstrate this, we must introduce The Task Type or the Type field:


By default, Type is set to Fixed Units. But there are actually three different Task Type variables:

  • Fixed Duration
  • Fixed Units
  • Fixed Work


Now to test Microsoft Project

Using our original scenario, let’s force Microsoft Project to solve for Duration.



We will leave Type set to Fixed Units and change Work to 80 hrs


Here is how Duration was calculated:

Work / Units = Duration
80 / 100% = 80
Or
80 / 100% = (80 / 8)
Or
80 / 100% = 10 days




Returning to our original scenario, let’s force Microsoft Project to solve for Work.


Leave Type set to Fixed Units and enter 10 days Duration


Here is how Work was calculated:

Units x Duration = Work
100% * 10 days = 80
Or
100% * 10 days = (10 * 8)
Or
100% * 10 days = 80 hours Work




Returning to our original scenario, let’s force Microsoft Project to solve for Units


Change Type to Fixed Duration and enter 20 hours Work


Here is how Units was calculated:

Work / Duration = Units
20 / 5 days = 50%
Or
20 / 5 days = 20 / (8 * 5)
Or
20 / 5 days = 20 / 40
Or
20 / 5 days = 0.5




To Review:

There are three different Task Types:

  • Fixed Units
  • Fixed Work
  • Fixed Duration
There are three different variables of the Scheduling Formula:

  • Units
  • Work
  • Duration
Depending upon how the Task Type is set in combination with which Scheduling Formula variable is altered dictates which variable Microsoft Project solves for.

The Task Type and Scheduling Formula Cheat Sheet will help you control how Microsoft Project “thinks”:


See The Microsoft Project Task Type and Scheduling Formula Cheat Sheet here.

See this article in Slide format here.

See this article in Video format here.

Purchase “The Cheat Sheet” Mouse Pad here.



Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Thursday, August 21 @ 07:47:34 CDT (1786 reads)
(Read More... | Score: 5)

MS Project: The Task Type and Scheduling Formula Cheat Sheet
PMConnection Articles

Understanding How Microsoft Project Thinks
Mouse Pad
Article
Slides
Video


Social Bookmark this page

RSS Feed for Exclusive Articles


Posted by webadmin on Thursday, August 21 @ 07:45:51 CDT (1138 reads)
(Read More... | Score: 3.66)

MS Project: How to Overlay Committed and Proposed Resource Information in Resource Graph
PMConnection Articles
Definitions:

Committed - A resource that is formally allocated to any task assignments they have within a project. This is the default booking type.

Proposed - A resource with a pending resource allocation to a task assignment that has not yet been authorized. This resource assignment does not detract from the availability of the resource to work on other projects.

1.  Within your schedule, click on >View, >Resource Sheet

2.  Insert the column Booking Type

3.  Code your resources either Committed or Proposed


4.  Develop your schedule assigning resources to tasks


5.  Click on >View, >Resource Usage

6.  Click on >Window, >Split

7.  Click anywhere on the bottom pane to activate


8.  Click on >View, >Resource Graph


The Resource Graph will now appear in the bottom pane. Note that this shows a graph for Peak Units. (this is not the graph we would like to leverage)

9.  Right click in the TimePhased portion of the Resource Graph and click on Work


10.  Right click in the TimePhased portion of the Resource Graph again and click on Bar Styles. The following dialogue box will appear:


11.  Under Selected resources, for Overallocated work (left side) show as Bar. For Allocated work, show as Bar. For Proposed Bookings, Show as Bar.

12.  Under Resource, for Overallocated work, Show as Don’t Show. For Allocated work, show as Don’t Show. For Proposed Bookings, Show as, Don’t Show. As a final step, check the Show Availability line. Here is how the dialogue box should be configured:


Click on OK!

13.  Now, click on the first resource name and lets examine the screen.


14.  Now click on the second resource name, and let’s inspect this view.


15.  Now click in the blank square in the upper left corner (above the ID number) to select all resources.


16.  Before leaving this exercise, let’s look at one more scenario. Let’s play with a Role.

17.  On the Resource Sheet, set Resource 2 Booking Type to Committed. Then add a resource named Role 1. Set the Booking Type to Proposed….AND…the Max Units to 0%.


18.  Now let’s say two new tasks are identified for our project. We are not sure exactly which resource we want to assign to those tasks yet, so we assign Role 1.


19.  Moving back to our combination view of Resource Usage on top and Resource Graph on bottom, let’s examine the details.


By clicking on Role 1, we see there is 40 hours of Proposed Work for the weeks of July 6th and July 13th. But notice there is no Availability line. This is because Role 1 is actually a placeholder and has no 0 hours of availability. We need to figure out which resource we can assign these tasks to.

20.  Now hold down the Control Key and click on Resource 1.


From this graph we see that if we moved this work from Role 1 to Resource 1, Resource 1 would become overallocated. We would be asking Resource 1 to do 80 hours worth of Work for the weeks of July 6th and July 13th.

21.  Let’s see if Resource 2 could handle the Work. Click on Role 1, hold down your Control Key and click on Resource 2.


Upon examining this graph, we can see that Resource 2 has the availability to handle this Proposed Work.

EXTRA: How to easily transfer the assignments from Role 1 to Resource 2.

1.  Click on the row to highlight Task 5.


2.  Hover over this row within the indicator column. You will see your cursor turn into 4 arrows. Now hold down with your left mouse button and drag this task until it is under Task 4. Release the left mouse button.


3.  Click on the row to highlight Task 6. Hover over this row within the indicator column. You will see your cursor turn into 4 arrows. Now hold down the left mouse button and drag this task until it is under Task 5. Release the left mouse button.

4.  Click on Resource 2


Notice that Role 1 no longer has any assignments. Resource 2 has all 4 assignments and the graph indicates all this work can be done without causing Resource 2 to be overallocated.

Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Wednesday, July 09 @ 21:34:17 CDT (1209 reads)
(Read More... | Score: 5)

MS Project: Dumbing Down Microsoft Project
PMConnection Articles
Creating a Checklist or To-Do List in Microsoft Project


Ok…so you’ve got a VERY small project, or simply a collection of tasks that you need to complete. Call it a checklist or a To-Do list if you will. You know MS Project is a powerful tool and can be used to manage very complex projects. But you don’t really need a full blown dynamic schedule, so you are thinking of creating your list in Excel…WAIT!!!

This article will show you how to “dumb down” Microsoft Project for the purposes of creating a simple To-Do list. You’ll learn some easy, yet powerful features that will make creating and maintaining a To-Do list easier in Microsoft Project than Excel.



Building the List
1.    Open Microsoft Project and save your file with a meaningful name
2.    Modify the Gantt Chart View
       a.    Hide the Indicator column
       b.    Hide the Duration column
       c.    Hide the Start column
       d.    Hide the Predecessor column
       e.    Insert % Work Complete
       f.    Insert Notes column
      g.    Slide the vertical divider for the Gantt Chart all the way to the right



3.    Add Data
      a.    Input task within Name column
      b.    Input targeted finish date within Finish column
      c.    Input the name of the person or people responsible for the task in the Resource Names column



4.    Save a Baseline
       Click on >Tools, >Tracking, >Save Baseline




Managing the List

5.    Input Updates
       a.    Modify Finish date as necessary
       b.    Update % Work Complete
       c.    Add Notes to tasks as needed

 



Reporting from the List
6.    Print the list in its entirety
7.    Filter the list
       Click on >Project, >Filter and you can quickly filter for:
       a.    Incomplete tasks


Result:


      

       b.    Complete tasks


Result:


      

       c.    By Resource



Result shows any task assigned to Sam:



       d.    By Date Range




Result:



8.    Autofilter
You can enable the Autofilter for all columns.

    

You can now click on the auto filter dropdown for any column and leverage it to filter the list. A good example is you could click on the dropdown for Name, use the custom option and filter for only the tasks that contain the name “furniture”.


Result:


9.    Compare to Baseline
By inserting the Baseline Finish and the Finish Variance columns, we can see our original targeted finish dates and how far tasks have slipped.


10.    Insert Project Summary task to get overall % Work Complete
Click on >Tools, >Options, >View tab and check “Show project summary task”


Result:


11.    View as Calendar
Click on >View, >Calendar


Question:  Now…can you do all that in Excel?
Answer:  Yes, but not near as easily!!!

CAUTION:  Using this approach removes the dynamic scheduling capabilities of Microsoft Project.  In other words, if the tasks on your To-Do list must be done sequentially, and you experience a delay in one of the “upstream” tasks, you will need to manually change the dates of all the downstream tasks.  This is not the best approach when working with Microsoft Project.  However, as the article started, if you currently create and maintain To-Do lists in Excel, you may find using this approach in Microsoft Project to be more beneficial.


Social Bookmark this page

RSS Feed for Exclusive Articles

Posted by webadmin on Sunday, April 20 @ 09:03:53 CDT (1771 reads)
(Read More... | Score: 3.75)

MS Project: Microsoft Project Certifications Insight
PMConnection Articles
At the time of this article, Microsoft has moved three of the four proposed certifications that align with their project management tools to a "production" state.  Finding one page on Microsoft's site or any website that pulls the details of these certifications together is virtually impossible.  Thus the reason for this article!
 

  Exam
Name
Microsoft Office Project 2007, Managing Projects
Microsoft Office Project Server 2007, Managing Projects Microsoft Office Project Server 2007, Configuring Microsoft Office Project Server 2007, Managing Projects and Programs Microsoft Office Project Portfolio Server 2007, Managing Portfolios* Exam
Number

70-632 70-633 70-639 70-634 70-635* Tool Focus Microsoft Project 2007
Microsoft Project Professional and Project Server 2007




Microsoft Portfolio Server 2007 Credential Microsoft Certified Technology Specialist (MCTS)

Microsoft Certified Technology Specialist (MCTS)
Microsoft Certified Technology Specialist (MCTS) Microsoft Certified IT Professional (MCITP) TBD* Prerequisite N/A N/A N/A Microsoft Certified Technology Specialist (MCTS)
TBD* Date Available

July 2007 October 2007 January 2008 January 2008 4th Quarter 2008 Preparation Guides How to Prepare
for the Microsoft Project 2007 Certification Exam


Preparation Guide for Exam 70-633 Preparation Guide for Exam 70-639 Preparation Guide
for Exam 70-634
TBD* Exam Prep Questions Free Microsoft Project Certification Exam Prep Questions

        Exam Prep Books Managing Projects with Microsoft® Office Project 2007

Managing Projects with Microsoft® Office Project Server 2007       Self Paced Training Products

Other Microsoft Project Books Other Project
Server Books
Other Project Server Books Other Project
Server Books
  Exam Prep Courses

Course 5927 Course 5928
Course 5929




  Process Focus

Project Management Project
Management Server and Network Administration Project and Program Management Portfolio Management Additional References
Microsoft Project Microsoft Project Server Microsoft Project Server Microsoft Project Server Microsoft Portfolio Server
The tests are NOT taken using the software.  They all consist of multiple choice questions.  You get 2.5 hours to complete the exams.

Register for these exams with Prometric.  The cost is $125.00

Get a second chance to pass your Microsoft Certification exam—free offer!

Learn where the MCTS & MCITP certifications fit within Microsoft's certification framework - Here

Interesting Article "The Value of Certification"

*Exact details not yet available.

This site will be updated as more information becomes available.

Number of Microsoft EPM Certifications worldwide



Social Bookmark this page

RSS Feed for Exclusive Articles


Posted by webadmin on Saturday, March 22 @ 23:47:30 CDT (3359 reads)
(Read More... | Score: 0)

Feature Product
how_to_build_a_p_thumbnail by you.

Website Sponsors
PM Products
"Project Management Software"

PgMP Tools
"Helping you with the PgMP Certification"


Request advertising information

Survey
Is Project Management a Profession Yet?

No - and never it never will
Yes, fully - like law, medicine, or academia
No, not yet - could reach second-tier profession
Yes, but second-tier - like engineering
Undecided/unclear - status is indeterminate



Results
Polls

Votes 155

Buzzword

Need a Template?
Free Project Management and Microsoft Project Schedule Templates here!

RSS Feed

     

Total Hits
We received
5241253
page views since January 2006

Website Stats
March 2009

Page Views: 208,918
Links:             5,526
Articles:              58
Subscribers:    3,420

Looking for Books?
Try this link!!

PDU's Via Web
Search Event Calendar for "web" or click here.

The Project Management Mall - Now Open!



Copyright 2005-2009 PMConnection.com. All Rights Reserved.
http://www.pmconnection.com
a
PHP-Nuke Copyright © 2005 by Francisco Burzi. This is free software, and you may redistribute it under the GPL. PHP-Nuke comes with absolutely no warranty, for details, see the license.
Page Generation: 1.74 Seconds