Rolling up Resources in MS Project
Date: Sunday, November 14 @ 08:38:44 EST
Topic: PMConnection Articles



Question:

How do I see the effort or work by resource at a summary task? See the example below



Answer:

1. Create the scenario:

clip_image002

2. Switch to Resource Usage View:

clip_image004

3. Click on Project, Group By, Customize Group by:

4. Check: Group assignments, not resources

5. Input Task Summary Name as the first Field Name, then select Assignment under field Type.

6. Input Name as the second Field Name.

clip_image006

7. Click on OK

Result:

clip_image008

Desired Result:

Summary Task
13 hrs of a BA 
11 hrs of a PM