3. You create a project plan and have two tasks that need to be linked. You want to ensure the "Define Business Model" task does not end before you complete the "Define Outsourcing Strategy" task.
4. As per your project plan, a resource is scheduled to work on a task for 20 hours. The resource reports 30 hours of actual work, however. You have 10 hours of overtime work reported for the resource. You want to calculate the cost for the overtime, using minimum administrative effort and making minimum modifications to the project file.
What should you do?
A. Manually calculate the overtime.
B. Insert the
Overtime work field to calculate the overtime.
C. Extend the total work duration to 30 hours.
D. Separate the overtime as a new task and then assign a new cost to the overtime task.
Click here for answer #4
5. You are using a project plan in Microsoft Office Project 2007. You want to view only those tasks on which the resource Hannah is working. You are in the
Task Usage view.
What should you do to achieve the objective?
A. Print a
Who Does What report.
B. Change the view to the
Resource Usage view.
C. Change the view to the
Tracking Gantt view and apply the
Using Resource filter.
D. Change the view to the
Tracking Gantt view and apply the
Resource Group filter.
Click here for answer #515 More Free Microsoft Project Certification Exam Prep Questions